Homer harbor panel drops added legal fees as float costs climb

Businesses applying for city subleases in Homer could avoid unexpected legal bills after the Port and Harbor Advisory Commission voted Nov. 12, to remove additional legal charges from a proposed fee schedule.

The unanimous recommendation came during a review of the city’s 2027 terminal tariff, which governs charges for harbor services and operations. Commissioners also backed two Spit lease applications and examined ways to reduce the cost of a major harbor renovation.

Port Director Bryan Hawkins said the inflation adjustment would be finalized closer to December, with the increase expected to fall slightly below 3%.

The amended tariff is expected to go before the Homer City Council in January.

Sublease scrutiny

Much of the discussion focused on lease applications involving parent companies and their subsidiaries, which Hawkins said can require extra work from city staff and attorneys.

To help cover those costs, staff proposed charging applicants additional legal fees when their business arrangements made the review process more complicated. Hawkins said the problem has arisen when applicants create subsidiaries or change which company holds a proposed lease partway through negotiations.

Commissioner William Roth questioned the proposal, saying businesses should know what they could expect to pay before applying. “As a business owner, not having a variable like that for an application would be intimidating,” he said.

David Atwood suggested setting a maximum charge, but the commission ultimately voted 4-0 to recommend removing the legal-fee provisions from both Homer Spit and airport sublease applications before unanimously approving the amended tariff for consideration by the City Council.

Separate changes would allow short-term recreational boat rentals under harbor rules that generally prohibit subleasing assigned moorage stalls. Hawkins said staff wanted to accommodate businesses renting boats to customers for a day or two without opening the door to transferring moorage privileges between businesses.

Two Spit leases recommended

Commissioners additionally voted 4-0 to recommend a proposed 20-year lease for Within the Wild Adventure Company on Homer Spit Lot 88-2 — despite questions about the decision to offer existing building owners an opportunity to apply without first soliciting competing proposals.

City Manager Melissa Jacobsen explained that the property’s previous 30-year lease expired in 2025, leaving several buildings under separate ownership despite the original ground lease requiring a single lessee.

The city subsequently provided temporary leases while determining how to address the buildings, but Within the Wild was the only party to pursue a long-term agreement. According to the application details, the company anticipates spending between $300,000 and $600,000 on improvements.

Roth raised concerns about the lack of detailed development estimates and the company’s financial losses from 2023 through 2025, which had decreased each year and whether the company had sufficient resources to move forward with the project. The company plans to seek additional financing through First National Bank Alaska. Despite those concerns, commissioners supported forwarding the application to the council.

A second unanimous vote recommended approval of a new lease for Pier One Theatre, a nonprofit that operates its seasonal theater in a city-owned building near the Fishing Hole.

Executive Director Jennifer Norton said one major improvement had been completed, as part of an Alaska Public Risk Management inspection, while the remaining work was expected to take place in the spring.

“We feel confident we can take care of that prior to involving any more people in the building,” she said.

Float replacement costs climb

Elsewhere, commissioners reviewed construction estimates for the System 4 float replacement which have reached approximately $22 million, an increase from the earlier budget of roughly $17 million.

Homer secured an $11.2 million federal Port Infrastructure Development Program grant earlier this year to help replace the deteriorating system, which was originally constructed in 1964 and serves approximately one-third of the harbor’s vessels.

Hawkins said the city is working with Turnagain Marine Construction and project management firm Moffatt & Nichol to supplement new floats, utility connections, replacement pilings and a longer covered gangway at Ramp 6.

An approximately $800,000 dry fire suppression system is among the potential savings that Hawkins said the fire chief determined was not required. Electrical installations proposed for smaller vessel stalls are another area under review.

Replacing the Ramp 6 gangway could cost nearly $2 million, and eliminating a proposed BB float extension could save an estimated $1.5 million. However, Hawkins cautioned that preserving older structures could create future problems if they need to be replaced after new floats have been installed around them.

2027 dredging at risk

Although the U.S. Army Corps of Engineers completed maintenance dredging at Homer this fall; the proposed federal budget does not include funding for the same work next year, meaning routine harbor dredging could be interrupted in 2027.

Similar concerns affect Ninilchik, Dillingham and Nome, prompting efforts through the Alaska Association of Harbormasters and Port Administrators to seek help from Alaska’s congressional delegation.

Without additional federal assistance, Homer could end up missing its customary fall dredging.

For the System 4 replacement, meanwhile, the city hopes to complete design work and arrange materials and construction contracts in time for work to begin in fall 2027.

With construction planned for fall 2027, the city now faces some difficult decisions about what to keep in the project and what it can do without.

Homer News

Leave a Reply