A Fritz Creek house built too close to a property boundary can stay, but borough officials want to prevent similar mistakes.
The Kenai Peninsula Borough Planning Commission unanimously approved the exception during its regular meeting Monday, Nov. 16, allowing a one-story house in Lind Subdivision to extend into a normally prohibited area.
According to staff, the structure extends 13.1 feet into the setback at one end and 10.3 feet at the other. The encroachment borders Buena Vista Street, but does not connect to any other streets, and Homer Electric Association has transformers at both ends.
Residents reach the property from Hammock Circle through an existing driveway crossing neighboring parcels, and because Buena Vista Street is undeveloped, staff determined the encroachment would not create traffic or sight-distance concerns.
The discussion raised concerns about property owners building too close to lot lines without having their land surveyed first.
Planning Director Robert Ruffner said that without a general building permit requirement, there are few opportunities to warn property owners about setback rules before construction begins. While the planning department works with surveyors to share that information, reaching people who build without hiring one is more difficult.
“I think we’re going to continue to see them,” Ruffner said of setback encroachments, unless the borough establishes some form of building permit requirement.
Commission Chair Jeremy Brantley suggested using radio announcements to inform property owners about the rules and considering higher penalties for building too close to property lines.
Ruffner said he would discuss the ideas with the mayor, but the commission took no action.
Road access draws opposition
Elsewhere, property owners near Windchime Street in Salamatof opposed a proposal to eliminate part of the public road access.
The application seeks to vacate a 33-foot-wide eastern portion of Windchime Street south of a proposed cul-de-sac, adjacent to Government Lot 47.
John Benavides and his son Casey opposed the proposal, saying it could cut off access to Casey’s property and make it harder to bring electricity to the site.
Casey Benavides said he had already applied for permission to clear the existing access route and had contacted Homer Electric Association about extending service from Williams Road.
His property does not connect to some of the alternative routes identified in the application, he told commissioners. “Once an established easement is vacated, restoring that access may be extremely difficult or impossible,” Benavides said.
His father argued that giving up the right of way could affect future development opportunities for neighboring parcels.
Commissioners did not vote on the application. In a separate unanimous decision, the commission approved a utility easement vacation associated with Pettifogger’s Place Subdivision in the Cohoe area to accommodate the relocation of Keyros Avenue to the northern portion of the property. The owners plan to combine parcels to expand an existing campground. A new 10-foot utility easement will be established alongside the relocated road.
Supreme Court upholds gravel pit denial
Commissioners later revisited one of the borough’s longest-running land-use disputes after the Alaska Supreme Court upheld their decision to deny a gravel pit permit near Anchor Point.
Deputy Borough Attorney A. Walker Steinhage reviewed the court’s Oct. 23 ruling on Beachcomber LLC’s 2018 application to mine gravel on about 27 acres of its 41.72-acre property.
The commission initially rejected the application over concerns that the surrounding terrain would carry noise from the gravel pit and leave the operation visible to nearby residents.
Following several appeals, the commission approved the permit in 2019 after a hearing officer ruled that applications meeting the conditions in borough code could not be denied.
A Superior Court ruling later gave commissioners the authority to reject permits if those conditions failed to adequately address the impacts, leading to another denial in 2022.
The Supreme Court affirmed that denial, finding sufficient evidence to support the commission’s conclusion that berms and other measures could not adequately reduce the proposed operation’s impacts on nearby properties.
Under the ruling, commissioners cannot deny a permit simply because neighbors oppose it. Their decisions must be supported by evidence and borough code.
Steinhage said commissioners need to clearly explain the evidence behind their decisions so courts can understand how they reached them.
Several commissioners who served during the Beachcomber case recalled how difficult the process had been.
“I was there through every single step of this,” Commissioner Virginia Morgan said. “It was excruciating.”
The borough amended its material-site regulations in 2023, meaning the Supreme Court evaluated the Beachcomber application under rules that have since changed.
Commissioners will revisit those lessons in early 2027 during a workshop on documenting and explaining their decisions.