State proposes 5,805-acre land sale for Bradley Lake project
United States
Breaking News:
Washington DC
Sunday, Nov 29, 2026

Nearly nine square miles of state-owned land northeast of Homer could change hands as Alaska moves toward a major expansion of the Bradley Lake hydroelectric project, which supplies electricity to communities from the southern Kenai Peninsula to Fairbanks.
The Alaska Department of Natural Resources (DNR) opened public comment Friday, Oct. 2, on a proposed noncompetitive sale of approximately 5,805 acres to the Alaska Energy Authority (AEA), the state corporation responsible for developing and overseeing energy infrastructure.
Located east of Kachemak Bay, about 23 miles northeast of Homer, the property is associated with plans to expand Bradley Lake’s generating capabilities by drawing additional water from the Dixon Glacier area.
Residents and government agencies have until 5 p.m. Nov. 3 to comment on the preliminary decision and a related proposal to close the land to new mineral exploration claims.
The public notice does not specify the sale’s financial terms, but under Alaska’s public and charitable land disposal provisions, state law allows qualifying public-purpose transactions to occur below appraised market value when officials determine doing so serves the public interest. DNR has not finalized the conveyance, and the proposed sale remains subject to public review.
For Homer and other communities connected to Alaska’s Railbelt electricity system, the land proposal comes as energy officials pursue a roughly $400 million investment intended to increase renewable power generation and reduce dependence on natural gas.
Bradley Lake, which began operating in 1991, already accounts for approximately 10% of the electricity produced annually for Railbelt utilities, according to AEA. Its output is delivered through a transmission network serving hundreds of thousands of Alaskans.
Unlike conventional power plants that require a continuous fuel supply, Bradley Lake generates electricity using water collected in its mountain reservoir. Expanding that supply would allow the facility to produce more energy using much of its existing infrastructure.
Plans call for capturing seasonal meltwater and surface runoff from Dixon Glacier, southwest of Bradley Lake, and directing it through an underground tunnel into the reservoir. Additional construction would include a diversion dam and modifications to the existing Bradley Lake dam. Federal documents describe raising the reservoir’s normal maximum operating level by about 16 feet through improvements to the spillway and dam embankment.
Based on the latest federal application, the combined changes are expected to increase average annual generation from approximately 436,000 megawatt-hours to 601,000 megawatt-hours, a gain of roughly 38%.
AEA estimates the expansion would also reduce natural gas consumption by approximately 1.5 billion cubic feet annually, helping address anticipated fuel shortages in Southcentral Alaska. Homer Electric Association is among the utilities expected to benefit from the additional power.
Progress toward construction has accelerated this year. Federal regulators accepted AEA’s application submitted June 30 to modify the existing hydropower operation for filing and opened a separate review process addressing the proposed changes. Meanwhile, AEA’s board endorsed a financing framework in July and forwarded the package to participating railbelt utilities for consideration. At the time, the authority estimated the expansion would cost approximately $400 million.
Beyond power production, the project also involves land management decisions affecting a remote portion of the southern Kenai Peninsula. As part of the proposed sale, DNR is considering Mineral Order 1340, which would close the entire 5,805-acre area to entry under state mining laws.
Agency documents state that the property contains no known mineral deposits and has no existing mining claims, but officials determined that future mining activity would be incomplete with the land’s intended use. Closure would prevent new mineral claims from being established within the designated area, although the land conveyance itself would require state approval.
Among the hydropower licensing issues are potential changes in Martin River water flows, aquatic connectivity, water temperatures, wetlands, and wildlife habitat. Because the expansion would redirect water that otherwise flows through the Martin River watershed, reviewers must consider how altered conditions could affect the surrounding environment. Those studies are part of the hydropower licensing process, rather than a separate approval granted through the proposed land sale.
DNR’s latest notice focuses instead on whether the state should convey the property to AEA and close it to future mineral entry.
Following the comment period, the agency will review submissions before issuing a final finding and decision. If no significant revisions are necessary, DNR may finalize the preliminary decision and mineral order without another public notice. Under the state’s notice procedures, only those who submit timely written comments will be eligible to appeal the subsequent decision.
Comments must be received by 5 p.m. Nov. 3 and can be submitted by email to dnr.noncompland@alaska.gov, by fax to 907-268-8916 or by mail to the Division of Mining, Land, and Water’s Land Conveyance Section, 550 W. Seventh Ave., Suite 460, Anchorage, AK 99501. Additional information, including the preliminary decision and proposed mineral order, is available through Alaska’s Online Public Notices website under project ADL 234892.
For now, the proposal represents another administrative step toward expanding Bradley Lake, with the future ownership and permitted uses of thousands of acres of state land still awaiting a final decision.